COMPANY PROFILE
PRODUCTIVITY, HOW IT IS MEASURED? WHAT STANDARDS ARE USED?
For machine productivity, 100% production per shift for every style of sock is calculated and the actual efficiency is calculated as under:

                                 Number Of Socks Actually Produced During The Shift
                                 -------------------------------------------------------------------
                                                Production At 100% Efficiency

For setting norms of efficiency, individual style and motif etc. are taken into consideration.

For labour productivity and quality assurance, VIL prefers to allot 6 to 7 Knitting Machines per operator, which includes mutually relieving operators, for continuos 24 hrs running.